Sullivan Square

  • Road work will continue at the Sullivan Square rotary. 
  • Work will include installation of traffic signal structures and paving.
  • The proposed work will require sequenced lane shifts along with some closing of lanes during off-peak hours. 
  • Work will continue on D Street.
  • Work will include drainage structure installation. 
  • The work will require some short-term lane closures and lane shifting. 
  • Work will continue at the Sullivan Square MBTA Station.
  • Work will include retaining wall installation and paving.
  • The work will be done with small crews in isolated areas outside of the roadway.
  • There is no anticipated impact to traffic. 

 

Route 16

  • Work will continue at Wellington Circle. 
  • Work will include traffic signal installation, roadway widening, curb and sidewalk installation. 
  • The work will be done with small crews working in isolated areas.
  • No/limited lane closures anticipated. 
  • Work will continue at Santilli Circle.
  • Work will include road widening and traffic signal installation. 
  • The work will be done by small crews working in isolated areas. 
  • No lane closures are anticipated.
  • Work will continue at Bell Circle.
  • Work will include traffic signal foundation installation.
  • The work will be done by small crews working in isolated areas.
  • No lane closures are anticipated.

 

Alford Street/Broadway (Route 99)

  • Roadwork will continue on Broadway.
  • Work will include traffic signal installation, roadway widening, and curb/sidewalk installation.
  • The work will require short-term lane closures. Some lane shifting may be required.
  • Two travel lanes southbound on Broadway will be maintained during morning peak hours and two travel lanes northbound on Broadway will be maintained during afternoon peak hours.

    EVERSOURCE TRAFFIC UPDATE

    (Information provided by Eversource)

    CHELSEA

    • Williams Street
      • There will be a single lane closure on Williams Street for utility excavation between Spruce and Arlington Streets on Monday, July 16, through Thursday, July 19, from approximately 7:00 a.m. to 3:30 p.m.
      • Expect alternating traffic patterns during this period.

    EVERETT

    • Robin Street 
      • There will be a single lane closure on Robin Street for utility excavation between Beacham and Dexter Streets on Monday, July 16, through Thursday, July 19, from approximately 6:00 p.m. to 3:00 a.m.
      • Expect alternating traffic patterns during this period.

    For any questions or comments, please contact the Eversource transmission hotline at 1-800-793-2202 or email TransmissionInfo@eversource.com.

     

     

    Week of Monday, July 9, 2018

    All work locations and durations are subject to weather.

    Sullivan Square

    • Road work will continue at the Sullivan Square rotary. 
    • Work will continue to include drainage structure installation, hydrant relocation, demolition of curb and installation of traffic signal foundations.
    • The proposed work will require sequenced lane shifts along with some closing of lanes during off-peak hours.
    • Work will begin on Spice Street.
    • Work will include drainage structure installation.
    • The proposed work will require some short-term lane closures and lane shifting.
    • Work will continue at the Sullivan Square MBTA Station.
    • Work will be done with small crews in isolated areas outside of the roadway.
    • There is no anticipated impact to traffic.

     

    Route 16

    • Work will continue at Wellington Circle.
    • Road widening, curb and sidewalk installation work will continue.
    • The work will be done with small crews working in isolated areas.
    • No/limited lane closures anticipated.
    • Work will continue at Santilli Circle.
    • Road widening and traffic signal installation work will continue.
    • The work will be done by small crews working in isolated areas.
    • No lane closures are anticipated.

     

    Alford Street/Broadway (Route 99)

    • Roadwork will continue on Broadway.
    • The work will include utility installation, roadway widening and curb/sidewalk installation.
    • The work will require short-term lane closures. Some lane shifting may be required.
    • Two travel lanes southbound on Broadway will be maintained during morning peak hours and two travel lanes northbound on Broadway will be maintained during afternoon peak hours.

    EVERSOURCE TRAFFIC UPDATE

    (Information provided by Eversource)

    CHELSEA

    • Williams Street
      • There will be a single lane closure on Williams Street for utility excavation between Spruce and Arlington Streets on Monday, July 9, through Thursday, July 12, from approximately 7:00 a.m. to 3:30 p.m. Expect alternating traffic patterns during this period.

    EVERETT

    • Robin Street 
      • There will be a single lane closure on Robin Street for utility excavation between Beacham and Dexter Streets on Monday, July 9, through Thursday, July 12, from approximately 6:00 p.m. to 3:00 a.m. Expect alternating traffic patterns during this period.

    For any questions or comments, please contact the Eversource transmission hotline at 1-800-793-2202 or email TransmissionInfo@eversource.com.

     

     

    Week of Monday, July 2, 2018

    All work locations and durations are subject to weather.
    No work is planned for Wednesday, July 4, due to the Independence Day holiday.

    Sullivan Square

    • Road work will continue at the Sullivan Square rotary. 
    • Work will continue to include drainage structure installation, hydrant relocation, demolition and installation of curb, sidewalks, and traffic signal foundations.
    • The proposed work will require sequenced lane shifts along with some closing of lanes during off-peak hours.
    • Work will begin on Spice Street.
    • Work will include drainage structure installation.
    • The proposed work will require some short-term lane closures and lane shifting.
    • Work will continue at the Sullivan Square MBTA Station.
    • Work will be done with small crews in isolated areas outside of the roadway.
    • There is no anticipated impact to traffic.

     

    Route 16

    • Work will continue at Wellington Circle.
    • Road widening work will continue.
    • The work will be done with small crews working in isolated areas.
    • No/limited lane closures anticipated.
    • Work will continue at Santilli Circle.
    • Road widening and drainage installation work will continue.
    • The work will be done by small crews working in isolated areas.
    • No lane closures are anticipated.
    • Traffic signal work will begin at Bell Circle.
    • Work installing traffic signal foundation will continue with small crews working in isolated areas.
    • The work will require closing small lengths of outside travel lanes for short durations.

     

    Alford Street/Broadway (Route 99)

    • Roadwork will continue on Broadway.
    • The work will include utility installation, roadway widening, and curb/sidewalk installation.
    • The work will require short-term lane closures. Some lane shifting may be required.
    • Two travel lanes southbound on Broadway will be maintained during morning peak hours and two travel lanes northbound on Broadway will be maintained during afternoon peak hours.

    EVERSOURCE TRAFFIC UPDATE

    (Information provided by Eversource)

    CHELSEA

    • Williams Street
      • There will be a single lane closure on Williams Street for utility excavation between Spruce and Arlington Streets on Monday, July 2, through Thursday, July 5, from approximately 7:00 a.m. to 3:30 p.m.
      • Expect alternating traffic patterns during this period. There will be no work on July 4th.

    EVERETT

    • Robin Street 
      • There will be a single lane closure on Robin Street for utility excavation between Beacham and Dexter Streets on Monday, July 2, through Thursday, July 5, from approximately 6:00 p.m. to 3:00 a.m.
      • Expect alternating traffic patterns during this period. There will be no work on July 4th.

    For any questions or comments, please contact the Eversource transmission hotline at 1-800-793-2202 or email TransmissionInfo@eversource.com.